11th Street Sidewalk
11th Street Sidewalk
Project Overview
complete sidewalks for the Safe Routes to School plan
11th Street is closed to through traffic from Baker Street to Ames Street beginning Monday, February 12. A Kansas Department of Transportation contractor, Killough Construction, is constructing a sidewalk along the west side of 11th from Ames to High Street.
Road closed between Baker and Ames Streets
Project Timeline
A rough timeline of the entire project is as follows:
- 11th street sidewalk, including the drainage infrastructure work between Baker and Ames, will continue through late March. The road will remain closed to through traffic during that time.
- The High Street segment from 4th to 2nd from approximately late March into early April.
- 2nd Street sidewalk from Fremont to Highway 56 in April.
- Quayle Street sidewalk from 6th to the Junior High in late April.
All of this timing is approximate and weather dependent.